Project Management Professional PMP · Free Practice Question Medium
Question 107
As an experienced project manager, you understand the importance of gathering project requirements early in the project life cycle to ensure your stakeholders are on board and agree with the project's goals. To be effective, you resort to a trained moderator's skills to facilitate the collect requirement process. Which of the following techniques for gathering requirements is best facilitated by a trained professional?
- A Multicriteria decision analysis
- B Nominal group technique
- C Focus groups
- D Interviews
Reveal correct answer
Correct answer: C
Explanation
Due to their highly interactive nature, focus groups are most effective when moderated by a trained professional who can collect their feedback effectively with a select group of individuals. Interviews are a face-to-face communication technique performed by a project manager to identify product functions and features. Nominal group techniques are methods to allow efficient group voting. Multicriteria decision analysis uses a decision matrix to evaluate several different criteria on project or product quality.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.