Project Management Professional PMP · Free Practice Question Easy
Question 108
Jordan has just completed the management of a small project that included replacing computer monitors in a single department of a large company. The project took four weeks to complete, was on budget, and was completed on time. The customers and the project sponsor are pleased with the outcome of the project. The project has been officially closed, and the team is ready to move on to other work. Of the following choices, what task should Jordan now complete, even for this small project?
- A Confirm that the project risks reports are finalized.
- B Perform a final earned value management analysis.
- C Meet with each stakeholder to confirm closure.
- D Archive the project information in the knowledge management system.
Reveal correct answer
Correct answer: D
Explanation
The best answer presented is to archive the project information. It is a good idea to archive project information for all projects, large or small, as the information might be needed later in the organization.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
