Question 56

Zane is a project manager at Camera Corporation and is planning a new project. During a recent stakeholder meeting, the stakeholders told Zane that every task was of the highest priority. What should Zane do in this situation?
  • A Escalate the issue to the steering committee.
  • B Prioritize every task as high.
  • C Agree, but assign different priorities on his own.
  • D Work with the stakeholders to stack rank the tasks.
Reveal correct answer

Correct answer: D

Explanation

While every task may be important, having all tasks ranked as the highest priority will result in the ranking losing its meaning. Zane should work with stakeholders to stack rank their objectives. Prioritizing every task as high is not the best answer because having all tasks ranked as the highest priority will result in the ranking losing all meaning. Agreeing, then changing the priorities, later risks negatively impacting his relationship with the stakeholders. The steering committee is not the best option as they are not responsible for ranking tasks.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need