Question 57

One of the responsibilities of a scrum master is to remove impediments, which will prevent the team from moving forward. All of the following are examples of impediments, except which one?
  • A Roadblocks
  • B Landmines
  • C Speed bumps
  • D Blockers
Reveal correct answer

Correct answer: C

Explanation

Speed bumps are not considered impediments that will prevent the team from moving forward. Landmines are risks that can "blow up" into big issues in the project. Blockers are risks that can prevent the team from moving forward. Roadblocks, like blockers, prevent the team from moving forward in the project.