Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 55
Which event produces a plan for process improvements that are required to be implemented in the next Sprint?
(choose the best answer)
- A Sprint Review
- B Daily Scrum
- C Sprint Retrospective
- D Sprint Planning
- E None of these events
Reveal correct answer
Correct answer: E
Explanation
According to the Scrum Guide, none of these events result in a plan for improvements that must be enacted during the next Sprint. The Sprint Retrospective results in a plan for improvements that the Scrum Team addresses as soon as possible, but it is not a requirement to have them worked on in the next Sprint. The other events have different purposes and outcomes.Discussion