Professional Scrum Product Owner I PSPO I · Free Practice Question Easy

Question 54

True or False: The Scrum Team must release at the end of every Sprint.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

False. While it is desirable to release at least once a Sprint, the decision to release the Increment is at the discretion of the Scrum Team. Releases can be made at any time when sufficient value is accumulated, not necessarily at the end of every Sprint.