Professional Scrum Product Owner I PSPO I · Free Practice Question Easy

Question 56

True or False: The Sprint for all the Scrum Teams working on the same product must start and end on the same date.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

Scrum does not require having aligned Sprints for multiple teams. The Scrum Teams self-manage and define the best option for them.