Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 53
True or False: Only valuable work should be kept in the Product Backlog.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: A
Explanation
Keeping non-valuable work on the Product Backlog increases its complexity and maintenance effort. Further, it might lead to missed opportunities and waste.Discussion