Project Management Professional PMP · Free Practice Question Easy
Question 6
Congratulations! You have finished the project work and are performing quality control. You are about to validate the scope, and management would first like to examine all the changes that have been requested and their statuses. Management wants to see which changes have been approved and which have been declined. Where can you find all of this information?
- A You will have records only of the change requests that have been approved because declined change requests are discarded.
- B The change log.
- C You will have records only of the change requests that have been declined because all approved changes are incorporated into the project scope, and the time and cost baselines are updated.
- D The risk register.
Reveal correct answer
Correct answer: B
Explanation
The change log includes the process for submitting, tracking, reviewing, and approving proposed changes. You will keep declined and approved change requests in the change log. You will keep declined and approved change requests in the change log. The risk register is not relevant to change request tracking.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
