Project Management Professional PMP · Free Practice Question Medium

Question 22

Sandra is the scrum master for a project that is just starting its first iteration. During a recent meeting with stakeholders, Sandra overhears one of them complain that they missed the deadline for adding a feature to the project's scope. What is Sandra's best response to this comment?
  • A The stakeholder can add the item to the backlog at any time.
  • B The stakeholder will have to convince the product owner the idea is important.
  • C The stakeholder is correct. Once the project begins, the scope is locked in.
  • D Invite the stakeholder to the next sprint review.
Reveal correct answer

Correct answer: A

Explanation

In an agile environment, anyone may add items to the project's backlog at any time. It is up to the product owner to determine their priority. There is no requirements deadline when adding to the backlog. Agile projects are designed to have a flexible scope, so they will not be locked when the project begins. The product owner is in charge of prioritizing items, not deciding which goes into the backlog. Sprint reviews are intended to share updates made in the prior iteration.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need