Stephanie is developing the project management plan. She has put together a detailed list of situations where the project could result in early project closure and listed some of the major ones under the risk register. She is also aware that her teammates have conflicting personalities and have backgrounds that starkly contrast one another. Which of the following events would not result in a project termination?
  • A Team members cannot work together.
  • B The organization no longer needs the project deliverables.
  • C Adequate funding is no longer available to complete the requirements.
  • D The requirements changed during execution to the point where the project is no longer feasible.
Reveal correct answer

Correct answer: A

Explanation

Team members not working together are not grounds for the project to close. The project manager should reduce conflict among team members, and if necessary, should be escalated to a higher level. Failure to acquire project funding, the project no longer generating business value, and the requirements changing where the project is no longer feasible are valid reasons for early project termination.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need