Benjamin is a project manager for a project which is ten weeks into a fifteen-week deployment. Benjamin is concerned that this project is behind schedule, so he compares its progress to another similar project he managed last year. What best describes this technique?
  • A Bottom-up estimating
  • B Benchmarking
  • C A case study
  • D Backlog review
Reveal correct answer

Correct answer: B

Explanation

Benchmarking is the process of using other similar projects or tasks to determine how yours is doing. Bottom-up estimating is a budgeting technique. Backlog reviews are conducted in agile projects to groom and update the backlog. A case study consists of in-depth research into a particular project.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need