Question 102

Janessa is a scrum master at Shaker Corporation and recently moderated a discussion between a few developers. During the discussion, the developers agreed upon a path forward. However, recently, some of the developers began to express concern over the agreement. What should Janessa do next?
  • A Meet with the developers and review their prior agreement.
  • B Escalate the conflict to the developer's scrum master.
  • C Do nothing, because as the moderator, Janessa is unable to intervene.
  • D Refer the developers to the steering committee.
Reveal correct answer

Correct answer: A

Explanation

Janessa should encourage the developers to continue their prior agreement. This will help build good faith and will encourage the team to work together. Doing nothing risks the situation escalating. Janessa's position as the moderator is to encourage the developers to continue their prior agreement and work together. Referring the developers to the steering committee is not a good choice as it is Janessa's role and responsibility to work with the team and coach them to a good resolution. Janessa is the scrum master in this scenario, so this is not a valid option.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need