Project Management Professional PMP · Free Practice Question Easy
Question 101
As the project manager for the Graham Project, Robert must create a contract for his customer. What two things must be included in the contract?
- A Signatures and a notary public stamp
- B The procured item's value and worth
- C An offer and consideration
- D Start date and acceptance of the start date
Reveal correct answer
Correct answer: C
Explanation
An offer and consideration is the best and correct response here. All contracts include an offer and a consideration. This response is incorrect because even though the project's start date may be specified, the acceptance of the start date is vague and unnecessary for all contracts. The value and worth of the procured product or service may not be explicitly defined in the contract; therefore, this response is incorrect. This response is incorrect because not all contracts require signatures and need notary public involvement.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
