PMI Agile Certified Practitioner PMI ACP · Free Practice Question Medium

Question 22

In the middle of an Agile project the business partner asks you, “If we adhere to the agreed-upon scope, when do you think the project will be finished, and how much will it cost?” What will you need to do in order to answer this question?
  • A Have a team meeting and logg everyone’s status
  • B Review the Kanban board
  • C Analyze the key performance indicators
  • D Check progress on the backlog
Reveal correct answer

Correct answer: C

Explanation

Analyze the key performance indicators is the correct answer. KPIs (key performance indicators) are the most reliable metrics to use. KPIs give you the progress rate, the remaining work to be done, the likely date of completion, and the likely costs remaining.The other responses are incorrect because the Kanban board, backlog, and statuses will only give you small pieces of information, whereas KPIs provide a broader picture of the project at any given time.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.