PMI Agile Certified Practitioner PMI ACP · Free Practice Question Medium
Question 23
During Sprint demonstrations on Jerry’s team, feedback requested on the product always begins with the most senior managers in the room and then proceeds to the newest delivery resources on the project team. Jerry’s Agile mentor weighs in on this process and is most likely to say:
- A Nothing, as the process is standard at their company
- B That this process can take far too long and should be amended to focus on managers
- C This process does not follow the Agile guideline of respecting individuals
- D Nothing if the Agile team has agreed on this approach
Reveal correct answer
Correct answer: C
Explanation
Jerry’s mentor is likely to respond with “This process does not follow the Agile guideline of respecting individuals.” When responses are ordered like this, it makes it appear that the value of the response from certain people is more than the value of other responses.Jerry should not “do nothing” since the Agile value of respecting individuals is not being followed, even if the company or team desires it. The length of the process is irrelevant.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
