Cole is a team member on a project. As he begins gathering requirements, what is a logical question he should ask, and have answered, first?
- A How much is in the budget?
- B How long will the project last?
- C How many team members will participate?
- D What is the business value?
Reveal correct answer
Correct answer: D
Explanation
What is the business value choice is the correct answer. To generate business value is the reason projects are carried out. The business risk and the impact of not doing the project must be considered. The other responses are incorrect because the budget, duration, and member participation are determined once the value-driven delivery is identified.Discussion