PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 20

As the project manager for his Agile team at Muffin Manufacturing, Alexy is coordinating a workshop. He has asked the team to visualize how their release will go in a couple of months after a little bit of time has passed after the release. Alexy’s team must list everything that was delivered and also describe how the release went. What is this activity called?
  • A Future visualization
  • B Back to the future
  • C Remember the future
  • D Post-release planning
Reveal correct answer

Correct answer: C

Explanation

Remember the future is the proper name for the technique depicted in this question and is the correct answer. This technique encourages teams to visualize what success looks like and think through how they can get there.The other terms are incorrect because they are not valid for this description; they are fictional; they are not Agile techniques for risk identification.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.