Prince2 7 Foundation · Free Practice Question Easy
Question 19
Which roles CANNOT be combined with the role of project assurance?
1. Project manager
2. Project support
3. User representative
4. Executive
- A 1 and 2
- B 2 and 3
- C 3 and 4
- D 1 and 4
Reveal correct answer
Correct answer: A
Explanation
OBJ 3.2.3: Project assurance must be independent of the project manager and project support. Project assurance is the responsibility of the project board. The executive and the user representative are both members of the project board, therefore they can be combined with the role of project assurance. The project board's responsibilities to assure itself that the project is being conducted correctly. The project board members each have a specific area of focus for project assurance, namely business assurance for the executive, user assurance for the user representative(s), and supplier assurance for the supplier representative(s).Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.