Prince2 7 Foundation · Free Practice Question Easy
Question 18
Which of the following is an objective of the initiating a project process?
- A To ensure that there is the authority to initiate the project
- B To ensure that all benefits have been achieved
- C To determine how baselines will be established and controlled
- D To capture the customer's quality expectations
Reveal correct answer
Correct answer: C
Explanation
OBJ 4.2: The objective of the initiating a project process is to determine how baselines will be established and controlled. The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.