Prince2 7 Foundation · Free Practice Question Easy

Question 18

Which of the following is an objective of the initiating a project process?
  • A To ensure that there is the authority to initiate the project
  • B To ensure that all benefits have been achieved
  • C To determine how baselines will be established and controlled
  • D To capture the customer's quality expectations
Reveal correct answer

Correct answer: C

Explanation

OBJ 4.2: The objective of the initiating a project process is to determine how baselines will be established and controlled. The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need