Prince2 7 Foundation · Free Practice Question Easy

Question 20

What must be used, as a minimum requirement, for applying the progress theme?
  • A Stage authorization
  • B Highlight reporting
  • C Work package authorization
  • D Checkpoint reporting
Reveal correct answer

Correct answer: A

Explanation

OBJ 3.7.2: To meet the requirements of PRINCE2, at a minimum a project must define its approach to controlling progress in the PID, manage by stages, set tolerances, and be managed by exception against them, review the business justification when exceptions are raised, and learn lessons. Manage by stages includes the concept of using stage authorizations from the project board through the directing a project process.