LEED AP Building Design Construction LEED AP BDC · Free Practice Question Easy
Question 36
After the project received and accepted the final construction review, the LEED points were 58 point which means the project will get LEED Silver. However, the project owner wants the project to achieve LEED Gold. What can the team do to increase the number of points to 60 points?
-
A
The project can't achieve 60 points since the final construction review is completed.
-
B
The project owner can target another credit and use the alternative certification path to add additional points to the final project credits.
-
C
The project can send an official Credit Interpretation Request (CIR) to raise the issue and find a solution.
-
D
The project can ask for an appeal on the credits that were denied. The project might get a 60 point if the appeal got accepted.
Reveal correct answer
Correct answer: A
Explanation
The project can't achieve 60 points since the project team received and accepted the final construction review.Discussion