Project Management Professional PMP · Free Practice Question Easy
Question 154
Frank is the project manager for Project PU, which has just completed its planning stage. Besides sharing the work breakdown structure and other details about tasks and milestones, what additional information should Frank pass along to the project management office for their approval?
- A The roles and responsibilities matrix.
- B Frank's vacation schedule.
- C The product backlog.
- D A project resources requirements list.
Reveal correct answer
Correct answer: D
Explanation
Frank should ensure the project management office is aware of Project PU's resource requirements to plan and provide the resources as required for project success. Frank's vacation schedule may be necessary, but it is not the most critical piece of information to pass along. Predictive projects do not have a product backlog. The roles and responsibilities matrix is not the best answer to this question.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.