Question 153

Raquel is the scrum master for Project CF, which is in its third iteration and has a velocity of thirty-one story points. While reviewing the project backlog, tasks, and schedule, Raquel realizes that a specific vendor will be needed two weeks sooner than expected. What should Raquel do next?
  • A Review the vendor's contract to determine if they can be brought in earlier.
  • B Escalate the issue to the product owner.
  • C Delay the project for two weeks.
  • D Adjust the project schedule so that the vendor is not needed until it was initially planned.
Reveal correct answer

Correct answer: A

Explanation

Before taking any action, Raquel should determine if the vendor can be brought in two weeks earlier. The answer to this question will guide her next decision. In the real world, Raquel could simply call the vendor and ask, but this is not a practical answer to the question. The product owner is unlikely to be able to assist. Adjusting the project schedule runs the risk of Project CF being off schedule. Delaying the project runs the risk of Project CF being off schedule.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need