Larry is the project manager for Project Q, which is in its ninth week of implementation, is $5,000 over budget, and has a total budget of $100,000. Recently a team member let Larry know a critical task had somehow been missed during planning for Project Q. What should Larry do next?
- A Schedule the task for immediate work.
- B Bring up the task at the next sprint review.
- C Do nothing. Only planned tasks may be worked on in a project.
- D Submit the task to the change control board.
Reveal correct answer
Correct answer: D
Explanation
Despite its criticality, Larry should still follow the project’s change control processes, and this will ensure the task is properly integrated into the project. Slotting the task in for immediate work is not ideal as this likely violates the project’s change control process. Sprint reviews are only found in agile projects. Doing nothing risks critical work being missed by Project Q.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.