Project Management Professional PMP · Free Practice Question Medium

Question 147

Andrea is managing a project for a city park project. The project includes building a large-scale bridge that will connect a bike and walking path over a river in the park. Although all of the initial planning was completed months ago, the appropriate permits were obtained, and regulations have been followed; Andrea just received notice that the city has just issued a new change for the bridge. The recent change requires that the bridge length be eight feet longer than the initial plans. The city has made this change to make the bridge less steep. With this new change imposed by the city, which of the following choices will most likely not be impacted?
  • A Cost
  • B Quality
  • C Scope
  • D Schedule
Reveal correct answer

Correct answer: B

Explanation

Regardless of the length of the bridge, the same quality standards would apply throughout the project. Typically, the project’s scope, cost, and schedule would all be affected by the change in the length of the bridge.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need