Project Management Professional PMP · Free Practice Question Medium
Question 137
As the project manager for her organization, Phoebe is leading a large, technical project to upgrade the manufacturing equipment in the organization. Donald, the project sponsor, has asked Phoebe to relate the project requirements and activities to the project's strategic objectives. Which document contains the mentioned information that Donald is requesting?
- A Context diagram
- B Mind map
- C Scope statement
- D Requirements traceability matrix
Reveal correct answer
Correct answer: D
Explanation
The requirements traceability matrix will contain information that relates to project requirements and strategic objectives. A requirements traceability matrix shows each requirement as it moves through each phase of the project work to completion. A project's scope statement will not necessarily explicitly state the relationship between a project's requirements and the strategic objective; it will simply state the scope. While helpful, a context diagram does not relate the project requirements to the strategic objectives; it defines the scope. A mind map is useful to collect requirements but does not necessarily relate them to strategic objectives.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.