Project Management Professional PMP · Free Practice Question Easy
Question 138
Paulina is the scrum master for Project L, which is midway through its fifth iteration. Recently a project stakeholder approached Paulina and asked for access to project documents detailing progress. What should Paulina do?
- A Give the stakeholder access to the project information system.
- B Email the stakeholder an update.
- C Show the stakeholder the information radiators.
- D Refer the stakeholder to the product owner.
Reveal correct answer
Correct answer: C
Explanation
Paulina should refer the stakeholder to the project’s information radiators to get up-to-date information on Project L. The project management information system is not the best place to get updates on an agile project. Emailing updates is not the best method to provide updates to the stakeholder. Referring the person to the product owner does not resolve the problem or provide good communication.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.