Project Management Professional PMP · Free Practice Question Medium

Question 125

Marty is the project manager for his organization and he is trying to garner resources for a new project. The project will utilize software engineers, database administrators, and systems engineers. He will also need technical resources to help distribute the software as it is created. His manager explains to Marty that this organization is a weak matrix structure, and he must work accordingly. In a weak matrix organization, what best describes the role of a project manager?
  • A Support person
  • B Coordinator and expeditor
  • C Project manager with complete authority
  • D Functional manager
Reveal correct answer

Correct answer: B

Explanation

The role of a project manager in a weak matrix organization is one of a coordinator and expeditor. The project manager does not have much authority at all in a weak matrix organization. The project manager is more than just a support person. The project manager is not a functional manager in a weak matrix structure.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need