Question 124
A project plan gives a baseline for several factors. The project plan does not provide a baseline for which of the following?
- A Schedule
- B Scope
- C Control
- D Cost
Reveal correct answer
Correct answer: C
Explanation
Control is not a baseline and, therefore, the correct answer. The scope is a baseline included in the project plan, and it is also one of the features of the Triple Constraints of Project Management. Cost is a baseline included in the project plan. It is also one of the features of the Triple Constraints of Project Management. Scheduling is a baseline included in the project plan. It is also one of the features of the Triple Constraints of Project Management.Discussion