Virginia's agile coach at Snow's Watches discussed an issue with the gulf of evaluation in her new agile project. The first release of software that was built with this project likely was
- A Not what the developers really wanted to build.
- B Not what the customer really intended.
- C Not what the developers really delivered.
- D Not what the Scrum Master really understood.
Reveal correct answer
Correct answer: B
Explanation
The gulf of evaluation is a difference between what the customer intended and what was built. The gulf of evaluation is a misunderstanding between the delivery team and the customer. The gulf of evaluation does not have anything to do with what the Scrum Master wanted. The gulf of evaluation does not have anything to do with what the developers wanted. Internal processes should ensure that a first release is what the developers delivered, so that choice is not a reasonable option.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.