Project Management Professional PMP · Free Practice Question Easy

Question 93

You are the project manager of the Newton Construction Project. Your team for this project will include internal and external employees. Your project requires an electrician at month eight. This is an example of which of the following?
  • A Organizational interfaces
  • B Resource constraints
  • C Staffing requirements
  • D Contractor requirements
Reveal correct answer

Correct answer: C

Explanation

Because the project requires an electrician, a project role, this is a staffing requirement. Organizational interfaces are the touchpoints or connections between departments and this answer does not accurately describe the situation. Contractor requirements are relevant to the procurement issues, the minimum qualifications for the electrician, etc. Resource constraints deal more with the availability of the resource or the requirement to use the resource.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need