Project Management Professional PMP · Free Practice Question Easy
Question 93
You are the project manager of the Newton Construction Project. Your team for this project will include internal and external employees. Your project requires an electrician at month eight. This is an example of which of the following?
- A Organizational interfaces
- B Resource constraints
- C Staffing requirements
- D Contractor requirements
Reveal correct answer
Correct answer: C
Explanation
Because the project requires an electrician, a project role, this is a staffing requirement. Organizational interfaces are the touchpoints or connections between departments and this answer does not accurately describe the situation. Contractor requirements are relevant to the procurement issues, the minimum qualifications for the electrician, etc. Resource constraints deal more with the availability of the resource or the requirement to use the resource.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.