Project Management Professional PMP · Free Practice Question Medium
Question 86
Bruce has been assigned as the project manager for a virtual team that spans multiple different countries. This project is the fourth project Bruce has conducted virtually, but the first one where not every team member speaks English fluently. Bruce decides to create a team charter to avoid miscommunications within the team. Bruce arranges a web conference meeting so the team can develop the charter together. Which characteristic of a team charter should Bruce focus on first to avoid potential issues from the scenario?
- A Holding team members, including leadership, accountable to all the same principles.
- B Getting the buy-in of all team members, including ones who may have initially resisted being included.
- C Providing clarity and reducing confusion in cases where conflicting views arise.
- D Demonstrating the team's purpose and mission transparently to others in the organization.
Reveal correct answer
Correct answer: C
Explanation
As this project consists of team members from different countries and those who are not fluent in English, the characteristic that Bruce should focus on is providing clarity and reducing confusion in cases where conflicting views could arise. It is important to get buy-in from all team members, but this is not the first item Bruce and the team should tackle. Leadership and the project team should be held to the same principles, but the question is asking what Bruce should focus on first. Team charters do include a definition of purpose and the mission, but the question is asking what Bruce should focus on first.Discussion