Project Management Professional PMP · Free Practice Question Easy
Question 85
Lou, about to create cost estimates for his latest project, is the project manager for the Chandler Project. Of the following responses, which process input will help Lou the most?
- A WBS
- B Project scope
- C Requirements document
- D Parametric modeling
Reveal correct answer
Correct answer: A
Explanation
The correct answer is WBS, which is the input that is most helpful with project cost estimates. The project scope is not a cost estimating process input and is incorrect. A requirements document is not an input to the cost estimating process and is incorrect. Parametric modeling is not an input; it is a form of estimating.Discussion