Project Management Professional PMP · Free Practice Question Easy
Question 76
Julia is the project manager for a cosmetics and accessories company. One of their best-selling items is an ultra-high-grain emery board that provides an exceptionally smooth finish. The secret is to have 500 grains of super-fine sand per centimeter of an emery board. This requirement is publicized for all the manufacturers that Julia contracts with to procure production. What kind of project documentation is being used by Julia for knowledge transfer?
- A Quality management plan
- B Quality metrics
- C Risk report
- D Lessons learned register
Reveal correct answer
Correct answer: B
Explanation
Quality metrics are the key performance indicators and critical success factors applied to a project's deliverables. It is the degree of conformance to requirements and the product being fit for use. The lessons learned register is the place where previous knowledge about mistakes or best practices is kept. Quality management plans are measures used to ensure that quality stays above a certain level or within a certain range. A risk report is exactly what it sounds like a summary of overall project risks.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
