Project Management Professional PMP · Free Practice Question Easy

Question 75

The main reason that the team at Global Digital News limits their development work in progress is
  • A To best visualize and correct any major bottlenecks.
  • B Each programmer can have no more than two items in queue per the Kanban methodology.
  • C Due to the limited time of the product owner to visualize the work in each iteration.
  • D To ensure that the appropriate process is followed for each item.
Reveal correct answer

Correct answer: A

Explanation

One of the reasons to limit WIP in Kanban is to see where bottlenecks occur and correct them. There is no universal WIP limit. There is no correlation between following a process and WIP limits. WIP limits are not related to the product owner.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need