Project Management Professional PMP · Free Practice Question Easy

Question 49

Lucas is the project manager for the Orange Project. He is explaining to his project team the importance of completing lessons learned documentation. Why should Lucas's project team complete lessons learned documentation?
  • A So future stakeholders can see what the project's team has accomplished
  • B To ensure the closure of the project
  • C To help project teams in the future complete their projects with more efficiency.
  • D So management can see what the project's team has accomplished
Reveal correct answer

Correct answer: C

Explanation

Project teams should complete lessons learned documentation to help future teams finish their projects more efficiently and effectively. The other responses are incorrect because none of them include the intention of helping future project teams with lessons learned documentation.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need