Stephanie uses the remaining work key performance indicator to track the progress of her project. She can expect that the remaining work metrics that she provides will
- A Hold steady over time.
- B Steadily decrease over time.
- C Sharply drop after the initial MVP is released.
- D Mostly decrease, but at times increase if unanticipated work is found.
Reveal correct answer
Correct answer: D
Explanation
The remaining work should generally decrease each time an item is done, but increases are expected for defects and unanticipated new work. The remaining work will not steadily decrease if unanticipated work is added to the scope. The remaining work would not hold steady over time unless no one is working. The remaining work should not drop sharply after an MVP, as the time up to a release should exhibit a steady decrease in remaining work unless scope is added.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.