Benjamin is a project manager for a project which is ten weeks into a fifteen-week deployment. Benjamin is concerned that this project is behind schedule, so he compares its progress to another similar project he managed last year. What best describes this technique?
- A Bottom-up estimating
- B Benchmarking
- C A case study
- D Backlog review
Reveal correct answer
Correct answer: B
Explanation
Benchmarking is the process of using other similar projects or tasks to determine how yours is doing. Bottom-up estimating is a budgeting technique. Backlog reviews are conducted in agile projects to groom and update the backlog. A case study consists of in-depth research into a particular project.Discussion