Prince2 7 Foundation · Free Practice Question Easy

Question 19

Which roles CANNOT be combined with the role of project assurance? 1. Project manager 2. Project support 3. User representative 4. Executive
  • A 1 and 2
  • B 2 and 3
  • C 3 and 4
  • D 1 and 4
Reveal correct answer

Correct answer: A

Explanation

OBJ 3.2.3: Project assurance must be independent of the project manager and project support. Project assurance is the responsibility of the project board. The executive and the user representative are both members of the project board, therefore they can be combined with the role of project assurance. The project board's responsibilities to assure itself that the project is being conducted correctly. The project board members each have a specific area of focus for project assurance, namely business assurance for the executive, user assurance for the user representative(s), and supplier assurance for the supplier representative(s).

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need