Question 61
The agile team that Hans is working with has just completed an iteration and finished all tasks; he’s ready to move to the next iteration. How does Hans figure out which iteration should be next?
- A The PMO has already determined how the project should progress.
- B The team leader chooses the next iteration.
- C The team follows the project plan developed early in the project.
- D The customer continuously prioritizes the backlog.
Reveal correct answer
Correct answer: D
Explanation
The customer continuously prioritizes the backlog is the correct response. The team works through a prioritized list of items with the identifiable value provided by the customer. The other responses are incorrect. Agile teams know that plans created at the beginning of the project are fluid and subject to change, so attempting to follow an early developed plan may not be feasible. The PMO (project management office) does not determine the progression of the project. Lastly, the team leader doesn’t define the next iteration.Discussion