Oscar’s Agile team leader has scheduled retrospectives for the team after each iteration. Of the following, which best describes the purpose of this sort of meeting?
  • A It allows the team to prioritize new requirements.
  • B It allows team members to switch roles.
  • C It’s an opportunity for the team to inspect and improve their methods and teamwork.
  • D It lets the team voice their grievances.
Reveal correct answer

Correct answer: C

Explanation

The purpose of a retrospective is to allow a team to inspect and improve their methods and teamwork. Three questions should be asked and discussed during a retrospective: What is going well? What could we do differently? What areas could be improved? Solutions are validated when they are identified. If successful, they can be added as part of the ongoing process. If solutions fail, the team can decide to try something else or go back to the earlier process.The other responses are incorrect. The point of a retrospective is to improve upon the approach, not air grievances; the team doesn’t switch roles in a retrospective; before each iteration begins, the product owner will prioritize the product backlog, not in the retrospective.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need