PMI Agile Certified Practitioner PMI ACP · Free Practice Question Medium

Question 62

Kamal is the leader of his company’s agile team, which has decided to use the Crystal family of methodologies. What does the methodology chosen for each project depend on?
  • A The quality rate and number of developers combined
  • B A combination of the requirement and development defects’ impact and the size of the team
  • C The service level agreement required for product support
  • D The number of requirements and team size combined
Reveal correct answer

Correct answer: B

Explanation

The methodology chosen for each project depends on the impact that requirement and development defects will have combined with the size of the team. Crystal methodologies depend on the criticality of defects and size of the team. The other responses are incorrect because they don’t influence the methodology choice within the Crystal family.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need