Professional Scrum Product Owner I PSPO I · Free Practice Question Medium

Question 71

Which of the following are topics to be discussed during Sprint Retrospective?

(choose the best two answers)

  • A The Products Backlog order
  • B The team's collaboration
  • C Refine the Product Backlog
  • D Identify the most helpful changes to improve its effectiveness
Reveal correct answers

Correct answers: B, D

Explanation

The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. The Scrum Team identifies the most helpful changes to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint.