Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 72
True or False: It is a strict Scrum rule that every Product Backlog item must have detailed acceptance criteria before it's considered for Sprint Planning.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
While it is beneficial for Product Owners to have clear acceptance criteria for each Product Backlog item, it's not a strict requirement in the Scrum Guide. Acceptance criteria help clarify expectations, but there might be situations where the details are further refined in collaboration with the Developers during the Sprint. The essential thing is to have enough understanding to make informed decisions during Sprint Planning.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.