Question 72

True or False: It is a strict Scrum rule that every Product Backlog item must have detailed acceptance criteria before it's considered for Sprint Planning.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

While it is beneficial for Product Owners to have clear acceptance criteria for each Product Backlog item, it's not a strict requirement in the Scrum Guide. Acceptance criteria help clarify expectations, but there might be situations where the details are further refined in collaboration with the Developers during the Sprint. The essential thing is to have enough understanding to make informed decisions during Sprint Planning.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need