Question 70
Which two statements best describe the Product Backlog?
(Select the best two answers)
- A It changes as we learn more about the product.
- B Contains all tasks identified by the Developers.
- C It's used to create the project plan.
- D The Product Owner is accountable for it.
Reveal correct answers
Correct answers: A, D
Explanation
"Contains all tasks identified by the Developers".
- Tasks are identified in the Sprint Planning meeting or during the Sprint, and are captured only in the Sprint Backlog.
"It's used to create the project plan".
- There's no "project plan" in Scrum. Product Backlog is the closest thing to a project plan that we have in Scrum.