Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 54
True or False: The Scrum Team must release at the end of every Sprint.
- A TRUE
- B FALSE
Reveal correct answer
Correct answer: B
Explanation
False. While it is desirable to release at least once a Sprint, the decision to release the Increment is at the discretion of the Scrum Team. Releases can be made at any time when sufficient value is accumulated, not necessarily at the end of every Sprint.Discussion