Professional Scrum With Kanban PSK I · Free Practice Question Easy

Question 4

Should the cycle time of a Work Item be longer than the length of a Sprint?

  • A

    Yes

  • B

    No

Reveal correct answer

Correct answer: B

Explanation

No, however, it can happen that the cycle time is longer than the length of a Sprint. Ideally, the average Cycle Time should be way shorter than the length of a Sprint.

Remember, cycle time is the time elapsed between starting and finishing a work item.