Professional Scrum With Kanban PSK I · Free Practice Question Easy
Question 3
What is the Work Item Age and Workflow Stage of the Work Item where the blue arrow is pointing?

-
A
Work Item Age: 2
Stage: Code Review
-
B
Work Item Age: 2
Stage: In Progress
-
C
Work Item Age: 5
Stage: In Progress
-
D
Work Item Age: 5
Stage: Analysis
Reveal correct answer
Correct answer: C
Explanation
If you draw a horizontal and vertical line from a Work Item you can see that the Work Item Age (represented on the left axis) is 5 and the Stage is 'In Progress' as shown on the horizontal axis.

Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.