Professional Scrum Master I PSM I · Free Practice Question Easy

Question 79

Who within the Scrum Team is primarily responsible for estimating the effort required to complete Product Backlog items?

(choose the best answer)

  • A The Scrum Master
  • B The Scrum Team as a whole
  • C The Product Owner
  • D The Developers
Reveal correct answer

Correct answer: D

Explanation

According to the Scrum Guide, the accountability responsible for sizing Product Backlog items is the Developers. Sizing refers to the estimation or determination of the effort required to complete a Product Backlog item. The Developers collaborate and use their technical expertise to assess the size or effort needed for each item. This information helps in capacity planning and determining the Sprint Backlog during Sprint Planning.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need